Progress continues at pace across the Carlisle Southern Link Road (CSLR) project, with July proving to be another productive month on site. Our teams are working hard with several key areas seeing notable advancements.
Key Achievements in July
- The new roundabout at Newby West has been kerbed in preparation for surfacing in August.
- Works at the M6 Junction 42 end of the project have also progressed well following the closure of Newbiggin Road. The earthworks for the mainline are complete and the road box construction is ready for surfacing in this month.
- The Burthwaite Road closure also commenced allowing for the construction of the new Redcat Roundabout.
- Topsoil and hydro seeding are also progressing in areas that are nearing completion with fencing and hedges also going in.
Upcoming and Ongoing Road Closures
Newbiggin Road / M6 Junction 42 Closure
Closure Period: Monday 9 June – Friday 12 December 2025
Newbiggin Road, from Brisco Road/Wreay Road to Junction 42 of the M6, remains fully closed to all traffic, including vehicles, cyclists, pedestrians, and equestrians. This closure supports essential construction works and ensures public safety.
Diversion Route: via Durdar Road, Blackwell Road, St Nicholas, and London Road
View map and details
Access for Residents & Farmland:
- June – September: Access via M6 Junction 42
- October – December: Access via Brisco
Surfacing works have now commenced on this section, marking significant progress.
Ivegill Road Update
We continue to minimise disruption along the Ivegill Road. While a Traffic Regulation Order has been issued, this remains a precautionary measure.
We anticipate no further daytime closures, and any remaining work will be carried out overnight where possible.
We appreciate the continued patience and cooperation of local residents.
Burthwaite Road – Redcat Roundabout Construction
Closure Period: From Thursday 24 July 2025 – for approximately 2 months
To support safe construction of the new Redcat Roundabout, Burthwaite Road is now fully closed to through traffic.
Key works underway:
- Earthworks and surfacing
- Drainage and road infrastructure installation
- Final connections to the new roundabout layout
Diversion Route: via the reopened Ivegill Road (signed detours in place)
Newby West Roundabout Progress
The new, enlarged Newby West Roundabout is taking shape, with kerbing now complete.
Next steps:
- Surfacing and road marking works
- Overnight closures from 18–29 August, between 8pm and 6am
Diversion routes:
- HGVs: via Keswick
- Local traffic: via Dalston or alternative local routes
We are targeting full reopening by early September, helping to significantly improve traffic flow in this area.
Contact Us
If you have any questions or would like further details, please get in touch with the CSLR team via email: carlislesouthernlinkroad@cumberland.gov.uk
Thank you for your continued support as we deliver this transformational infrastructure project for Carlisle and the wider region.