Cumberland Council will be carrying out essential maintenance works on Durranhill Viaduct which are scheduled to begin in early January 2026. The structure carries the C1045 (Eastern Way), which links Warwick Road (A69) and London Road (A6), over Durranhill Road and the Carlisle–Settle and Carlisle–Newcastle railway lines.
Following a competitive tender process through the Capital Works Framework, Metcalfe Plant Hire Ltd has been awarded the contract for Phase 1 remedial works.
This phase will include:
- Replacement of bridge joints
- Installation of waterproofing
- Resurfacing of the carriageway and footways on spans 4–8
- Installation of bollards along the full length of the west footway
- Repairs to steel parapets (spans 1–8) and masonry parapets (span 9)
- Drainage improvements
Future phases will address joint replacement, waterproofing, and parapet repairs on the remaining spans. The second phase of the works are planned for 2026/27 financial year subject to funding.
The works are programmed to start on Monday 5 January 2026, and are expected to last approximately three months, subject to weather conditions. Completion is anticipated in April 2026.
Traffic management will include two-way lights and footway closures. One footway will remain open at all times, with a safe crossing point for pedestrians. Please follow all posted signage and use designated diversion routes during footway closures. These measures are essential to ensure the safety of both the public and construction personnel and will remain in place throughout the works.
Come and find out more about these works:
To provide more information about the project, a drop in event has been arranged. This is an opportunity for residents and road users to learn about the works, traffic management plans, and measures to minimise disruption.
Event Details:
Harraby Community Centre – The Bowman Lounge
Edgehill Road, Carlisle CA1 3SN
Monday 15 December 2025
4pm - 6pm
For further information, please visit the Cumberland Council website or contact the Highways Hotline on 0300 373 3736, quoting “Durranhill Viaduct – Remedial Works (Phase 1)”.