Local Plan timetable

Key stages and dates for preparing the Cumberland Local Plan.

The Local Plan timetable sets out the main stages for preparing the Cumberland Local Plan, including consultation periods, gateway assessments and publication points.

The timetable is required under the Town and Country Planning (Local Planning) (England) Regulations 2026, Part 2, Regulation 4, also incorporating a minerals and waste timetable.

Cumberland Council has given notice of its intention to commence preparation of a new local plan, which is to be referred to as the Cumberland Local Plan. The Cumberland Local Plan will set out the spatial vision and key objectives for the future development of the administrative area of Cumberland Council, excluding the area within the Lake District National Park. It will contain policies and site allocations to deliver these objectives and will include policies on minerals and waste.

The Council does not intend to prepare any supplementary plans at this time.

A statement that the local plan timetable is to have effect is required in accordance with Regulation 8 of the Town and Country Planning (Local Planning) (England) Regulations 2026 and for the purpose of this statement, the local plan timetable is to have effect and be made available from the 30 June 2026.

Timetable for plan preparation

Stage of plan preparationDate
Publish timetable30 June 2026
Publish Notice of Intention to Commence Plan Making30 June 2026
Scoping consultation - start14 September 2026
Scoping consultation - end23 October 2026
Gateway 1 - Self-assessment31 October 2026
Plan content and evidence consultation- start18 October 2027
Plan content and evidence consultation- end26 November 2027
Gateway 2 - Advice sought11 February 2028
Gateway 2 - Advice published24 March 2028
Proposed plan consultation - start12 June 2028
Proposed plan consultation - end4 September 2028
Gateway 3 - Advice sought2 October 2028
Gateway 3 - Advice published27 October 2028
Plan submitted for examination3 November 2028
Examination recommendations - published30 March 2029
Adopted24 April 2029

View or request a copy

You can view the timetable in person at:

  • Civic Centre, Rickergate, Carlisle, CA3 8QG (Monday to Thursday 9am to 5pm, Friday 9am to 4pm)
  • Allerdale House, New Bridge Road, Workington, CA14 3YJ (Monday to Thursday 9am to 4:30pm, Friday 9am to 4pm)
  • Market Hall, Market Place, Whitehaven, CA28 7JG (Monday to Friday 10am to midday, 2pm to 4pm)

To request a copy, contact the planning policy team:

Email: [email protected]

Schedule of amendments

The Local Plan timetable is reviewed regularly and updated when necessary.

The Town and Country Planning (Local Planning) (England) Regulations 2026, Part 2, Regulation 6 sets out requirements for reviewing and updating the timetable.

2 November 2026

The timetable has been updated to change:

  • Gateway 1 self-assessment from 30 October 2026 to 31 October 2026
  • proposed Local Plan content and evidence consultation period from 16 August to 1 October 2027 to 18 October to 26 November 2027
  • Gateway 2 advice sought from 3 January 2028 to 11 February 2028
  • Gateway 2 advice published from 11 February 2028 to 24 March 2028
  • proposed plan consultation from 15 May to 7 July 2028 to 12 June to 4 September 2028
  • Gateway 3 advice published from 30 October 2028 to 27 October 2028
  • planned adoption from 23 April 2029 to 24 April 2029

23 October 2026

No changes were required to the timetable. The CSV dataset was updated with the scoping consultation end date.

14 September 2026

No changes were required to the timetable. The CSV dataset was updated with the scoping consultation start date.

30 June 2026

The Local Plan timetable was first published.

Data downloads

The Council must follow the approved data standard to publish our Local Plan Timetable and Local Plan datasets so that we meet the requirements of the Planning Data (England) Regulations 2026.

These datasets will be updated when changes have been made to the timetable and when milestones have been met.